Whereas the proportion of value overruns had risen to 19.2% in September, it fell to 17.4% in October. The variety of tasks working delayed declined to 46.8% from 47.7% final month.
The anticipated value of tasks at Rs 29.1 lakh crore was Rs 4.31 lakh crore greater than the unique value as of November 1, based on the fee evaluation of 1,788 tasks, with a worth of Rs 150 crore and above, registered on the ministry’s portal.
“Out of the 1788 tasks, 50 tasks are forward of schedule, 611 are on schedule, 837 are delayed, 411 tasks reported value overrun, and 259 tasks reported each time and price overrun with respect to their unique mission implementation schedules,” the federal government said in its report.
Of the 837 delayed tasks, 54% had been delayed for over 25 months. Whereas the tempo of completion has been selecting up, the typical time overrun for tasks has remained unchanged from the earlier month at 36.94 months.
The federal government accomplished 183 tasks value Rs 1.84 lakh crore till October. In 2022-23, 329 tasks had been accomplished with a complete worth of Rs 3.07 lakh crore.Amongst ministries, water assets had the best value overruns with 41 tasks exceeding the unique value by 197%, adopted by Railways which confronted 51.8% value overrun. Roads, which accounts for over half of the overall tasks, had value overruns of simply 5.3%.When it comes to states, northeastern states had the best value overruns in comparison with the remainder of the nation.
The precise state of affairs on the bottom could replicate extra value overruns, the federal government said in its launch.
“It has additionally been noticed that mission companies are usually not reporting revised value estimates and commissioning schedules for a lot of tasks, which suggests that point/value overrun figures could also be underreported,” it stated.