“The (venture) award determine is 2,595 km throughout this era as in comparison with 5,007 km in the course of the interval in earlier 12 months. The ministry has constructed 4,474 km of nationwide highways as much as October in 2023-24 as in comparison with 4,060 km constructed as much as October in 2022-23,” MoRTH mentioned in its month-to-month abstract for the Cupboard for October 2023.
The ministry constructed 10,237 km NH in 2019-20 monetary 12 months, 13,327 km in 2020-21 and 10,457 km in 2021-22.
“lf the goal for award must be met for this 12 months, determination on the proposal for approval of the revised Bharatmala Section-1 or alternate programme must be taken expeditiously. Shortfall in award this 12 months will replicate within the progress of building in FY 2024-25,” it mentioned.
Bharatmala Pariyojana is the biggest freeway infrastructure programme in India that goals to develop 34,800 km of nationwide freeway corridors at an funding of Rs 5.35 lakh crore.
Section 1 of the programme contains improvement of about 24,800 km NH community equivalent to financial corridors, inter-corridor & feeder roads, nationwide corridors effectivity enhancements, border and worldwide connectivity roads, coastal and port connectivity roads, expressways in addition to 10,000 km of roads beneath stability Nationwide Freeway Growth Venture (NHDP).