
[ad_1]
The Infrastructure and Challenge Monitoring Division (IPMD) is remitted to observe central sector infrastructure tasks costing Rs 150 crore and above based mostly on the knowledge offered on the On-line Computerised Monitoring System (OCMS) by the undertaking implementing companies.
The IPMD comes below the Ministry of Statistics and Programme Implementation.
The report confirmed that the Muneerabad-Mahaboobnagar rail undertaking is the most-delayed undertaking. It’s delayed by 276 months.
The second-most delayed undertaking is the Udhampur-Srinagar-Baramulla rail undertaking, which is delayed by 247 months.
The third-most delayed undertaking, Belapur-Seawood-City Electrified Double Line, is delayed by 228 months.
The flash report for November 2022 comprises info on the standing of the 1,476 central sector infrastructure tasks costing Rs 150 crore and above.
As many as 756 tasks are delayed with respect to their authentic schedules and 304 tasks have reported further delays vis-a-vis their date of completion reported within the earlier month.
Of those 304 tasks, 58 are mega tasks costing Rs 1,000 crore and above.
About street transport and highways sector, the report acknowledged that whole authentic value of implementation of 769 tasks when sanctioned was Rs 4,33,744.86 crore, however this was subsequently anticipated at Rs 4,60,524.16 crore implying a value overrun of 6.2 per cent.
The expenditure incurred on these tasks until November 2022 was Rs 2,77,208.24 crore, or 60.2 per cent of the anticipated value of the tasks.
Equally, in railways, the entire authentic value of implementation of 173 tasks when sanctioned was Rs 3,72,761.45 crore, which subsequently elevated to Rs 6,24,583.37 crore, implying a value overrun of 67.6 per cent.
The expenditure incurred on these tasks until November was Rs 3,59,996.26 crore, which is 57.6 per cent of the anticipated value of the tasks.
About petroleum sector, it acknowledged that the entire authentic value of implementation of 154 tasks was Rs 3,81,885.12 crore however this was subsequently anticipated at Rs 4,01,966.41 crore — a value overrun of 5.3 per cent.
The expenditure incurred on these tasks until November 2022 was Rs 1,48,897.69 crore, or 37 per cent of the anticipated value of the tasks.